OPEN MATTER · LOCAL PLAN · THURROCK, ESSEX · SUPPLEMENTARY

Supplementary representation on Policy SS03

Arena Essex, Lakeside: the wildlife assessment is still wrong, the water and power are not confirmed, and national policy has moved against the allocation.

Filed with Thurrock Council on 10 November 2026 by Dr Jackie Lighten on behalf of Protect Langdon, within the extended consultation period. It adds to our representation of 12 October 2026, which stands. The full text follows below: the form answers, sections 1 to 8, then the documents relied on.

Form answers

Representor (Part A, questions 1 and 2): Dr Jackie Lighten, on behalf of Protect Langdon. Contact details are given on the consultation form. No agent.

Part of the plan (question 3): Policy SS03, Former Arena Essex site and fishing lake, Lakeside [1, pp.77 to 80], and the Habitats Regulations Assessment (HRA) as republished during the consultation [2].

Legally compliant (question 4(1)): No. See section 3.

Sound (question 4(2)): No. The policy is not justified and not effective (sections 4 and 5), and not consistent with national policy (sections 5 and 6).

Why (question 5): section 1 gives the conclusions. Sections 3 to 6 give the grounds, each with its document and page.

Modifications sought (question 6): delete Policy SS03 and the allocation, as in my representation of 12 October 2026. If it is not deleted, further modifications in section 7 are needed in addition.

Participation in the hearings (questions 7 and 8): Yes, as already requested. See section 8.

Relationship to my earlier representation: this document adds to my representation on Policy SS03 of 12 October 2026 [3], which stands in full. It does not replace it. Below, “the October representation” means that representation, and its paragraph numbers are given where a point adds to it.

Authored by Dr Jackie Lighten on behalf of Protect Langdon.

1. Summary

1.1 The HRA errors on SS03 remain. The Council replaced its HRA on 20 October 2026, six days after our representation on Policy SS18 showed that the August HRA had not assessed that allocation [4]. It was then reported as having reviewed the remaining consultation documents and found “no further issues” [5]. The replacement HRA still screens SS03 with text written for a town centre site, still relies on wastewater measures by a sewerage company that does not serve Thurrock, and still does not mention generators [2, pp.124, 125, 221]. Natural England’s response makes the same point about the water quality mitigation (paragraph 3.2). (Section 3.)

1.2 The water company has never assessed the scheme now proposed. The only enquiry made to Essex & Suffolk Water, in July 2024, sought 117.60 litres per second, mostly for water cooling, and the company said it would not permit a connection for that amount. No enquiry has been made since, and the company has carried out no modelling for the air-cooled design the applicant now describes [6, pp.2 to 3]. The Environment Agency says the deliverability of water supply for SS03 should be secured in the plan, not left to later connection enquiries (paragraph 4.6). (Section 4.)

1.3 The national system operator holds no grid application for the campus. The National Energy System Operator (NESO) holds no application, offer or agreement for a data centre to connect to the transmission network at Barking Grid Supply Point, and holds no record of advice to the Council on the Local Plan, SS03 or data centre demand [7, pp.2 to 3]. (Section 5.)

1.4 National policy has moved against the allocation. The Government’s draft National Policy Statement for Data Centres does not apply its presumption in favour of consent to data centres in the Green Belt, and expects evidence from electricity network bodies and water companies on capacity [8, paras 84, 107, 349]. In plain terms, a data centre in the Green Belt gets no presumption in its favour, and the plan must still show exceptional circumstances for changing the Green Belt boundary. It has not evidenced them for this use. Because SS03 is examined against the December 2024 NPPF, the August 2026 NPPF gives it very limited weight in the decision on the campus to the extent it is materially inconsistent with that Framework’s decision-making policies [9, Annex A para 2]. (Section 6.)

1.5 Two further modifications are sought if the policy is not deleted: correct the HRA for SS03 before submission, and obtain written confirmation of water supply and grid connection before submission. (Section 7.)

2. Why there is further information

2.1 The Council extended the consultation to midnight on 10 November 2026 after it published an updated HRA “following identification of an error in the previously published document”, and said the extension “will also give anyone wishing to respond more time to submit representations if they wish” [10].

2.2 The error was first raised by Protect Langdon. The HRA published in August 2026 did not assess Policy SS18 (Lower Langdon and Corringham Park Farm) under any name or number; its “SS18” was West Horndon. I raised this with Natural England in writing on 7 and 15 September 2026 and set it out in my representation on Policy SS18 of 14 October 2026 [4]. The Council replaced the HRA on 20 October. Its only written explanation, sent to Protect Langdon on 21 October, was: “Unfortunately, a site assessment was omitted in the previous Habitats Regulations Assessment (HRA) document. The site assessment had been undertaken previously; there was simply an administrative error in uploading an incorrect document”. It did not say which assessment had been omitted, or what had changed [11, section 7.1; Annex A, item A9]. The replacement adds a screening entry for Policy SS18 [2, pp.285 to 286].

2.3 Four things are new since the October representation was filed. Each is summarised here and set out in the section given. Copies of the two information responses are enclosed.

  • Essex & Suffolk Water’s reply of 27 October 2026 to my request under the Environmental Information Regulations 2004. The only enquiry it has received for the site, in July 2024, was for a water-cooled campus needing about 10.2 million litres a day, and it says it “would not permit a connection capable of supplying this amount of water”. No enquiry has been made since, it has done no modelling for the air-cooled design the applicant now describes, and its objection to the planning application stands [6, pp.2 to 3]. (Section 4.)

  • The National Energy System Operator’s reply of 28 October 2026 to my request. It holds no application, offer or agreement for a data centre to connect at Barking Grid Supply Point, where the applicant says the campus will connect, and states that “Total contracted transmission connected demand at Barking GSP is therefore 0”. It holds no record of any advice to the Council on the Local Plan, Policy SS03 or data centre demand [7, pp.2 to 3]. (Section 5.)

  • The Government’s draft National Policy Statement for Data Centres, published for consultation in October 2026. Its presumption in favour of consent does not apply to data centres in the Green Belt, and it expects evidence from electricity network bodies and water companies on capacity and constraints [8, paras 84, 107, 349]. (Section 6.)

  • The Regulation 19 responses of Natural England and the Environment Agency, both made after the October representation was filed. Natural England says the HRA’s water quality mitigation relies on a company that does not serve Thurrock, and that avoidance, as well as mitigation and compensation, will be required for the significant wildlife impacts on this site. The Environment Agency says the deliverability of water supply for SS03 should be secured in the plan. (Paragraphs 3.2, 4.6 and 6.6.)

3. The republished Habitats Regulations Assessment

3.1 The replacement HRA has no version control, and the Council says it has checked its other documents. The replacement was published on 20 October 2026 under the same title as the original, and its cover gives the same date, “July 2026”, with no new version number, no October date and no list of changes [11, section 7.3]. The version table on page 2 was changed without a note. In the original, the row for version 3, “Final report”, is dated 3 July 2026 [12, p.2]. In the replacement, the same row is dated 7 July 2026 [2, p.2]. The replacement is the HRA cited in this document. The Council was reported on 21 October 2026 as follows: “Officers have reviewed the remaining consultation documents and can confirm that no further issues have been identified” [5].

3.2 Every SS03 error set out in the October representation, paragraphs 4.1 to 4.5, remains in the republished HRA, on the same pages:

  • the screening entry for SS03 still reads: “This policy will result in development within the town centre” [2, p.221]. The site is not in a town centre [1, p.77];

  • on air quality, adverse effects on the Thames Estuary and Marshes Special Protection Area (SPA) and Ramsar site still “could not be ruled out at this stage, due to potential in combination effects due to the LTC” [2, para 7.4, p.131], and “additional evidence will be required to inform further HRA before the plan can be adopted” [2, para 7.9, p.133];

  • the water quality conclusion still holds “providing that the mitigation measures and improvements set out by Southern Water are followed” [2, p.125], relying on Southern Water’s “Gravesend Wastewater System” [2, p.124], while the Council’s Infrastructure Delivery Plan states that “AWS is the statutory sewerage undertaker for the borough”, AWS being Anglian Water Services [13, p.61]. Anglian Water is not named anywhere in the republished HRA. Natural England’s Regulation 19 response makes the same point: “Southern Water provides neither wastewater or supply services to the Thurrock area”, so “mitigation is currently not sufficient or applicable to conclude no AEOI”, that is, no adverse effect on the integrity of the protected site, and advises that “until these concerns have been addressed, the HRA is not sufficiently robust with regard to water resources and water quality” [14, p.5]; and

  • the word “generator” does not appear anywhere in the republished HRA, although the campus would rely on standby diesel generators (October representation, Appendix A, A6).

3.3 The HRA records a Green Belt change that no policy makes. Its screening of the plan’s employment policy describes the plan as allocating “27 hectares of land at the former Essex Arena site for the provision of new data centres through amendments to the Green Belt boundary” [2, p.209]. No policy in the plan states what the amended boundary is (October representation, paragraph 3.3(e)).

3.4 The Council’s check of its documents did not find these errors. They were set out in our October representation, which the Council had held for more than a week when the statement was made. The one error that was corrected had first been raised by Protect Langdon (paragraph 2.2). Residents who asked the Council in writing what the replacement had changed were not told [11, section 7.2]. On the HRA’s own conclusions, the integrity test is still not met for air quality, and the water quality conclusion still rests on measures by an undertaker that does not serve the borough. Policy SS03 is therefore not legally compliant, and the plan cannot lawfully be adopted while it contains SS03 on this assessment.

Fails: legal compliance (Conservation of Habitats and Species Regulations 2017, regulation 105).

4. Water supply

4.1 The only enquiry the water company has received was for a water-cooled campus, and the company would not supply it. Northumbrian Water, trading as Essex & Suffolk Water, has released its response to the July 2024 pre-planning enquiry for the site [6, pp.2 to 3]. The enquiry sought 117.60 litres per second, about 10.2 million litres a day (117.60 x 86,400 seconds). The company’s network had the capacity, but: “As we are an area of limited water resources, which need to be balanced to ensure we maintain supply for our domestic customers, NWL would not permit a connection capable of supplying this amount of water to be made to our network if a formal water service application is submitted due to excessive usage.” It added: “100.3 l/s of the requested water capacity for this proposed development is for non-domestic use, for a water-cooling solution, and we would expect the development to use other methods of cooling rather than treated mains water supply” [6, p.3].

4.2 No enquiry has been made since. “There have not been any new pre-planning enquiries (PPE) submitted to ESW on this project since July 2024.” The company asked the applicant for a new submission on 13 August 2025, “however the client has still not provided this. At present, there is no valid PPE and therefore we have not been able to complete any network capabilities/modelling on this site” [6, p.3]. The company confirms that its objection to the planning application stands [6, p.3], as it told the Council on 13 August 2026 [15].

4.3 The applicant now describes a design the water company has never been asked to assess. The applicant’s note of 13 November 2025 states that the campus will use “high-efficiency air-cooled chillers with free-cooling”, and that “no evaporative cooling is proposed and therefore no process water demand arises for server cooling; water use is limited to normal domestic and office needs” [16, p.1]. That design has not been put to the water company (paragraph 4.2). The only demand the company has assessed is one it would not supply.

4.4 The plan therefore allocates a site for a use whose water supply has not been confirmed for any design. This adds to the October representation, paragraphs 6.10 to 6.12, which records the company’s objection, the warning in the Council’s Water Cycle Study Scoping Report of March 2024 that the company “may not be able to supply new businesses” with large non-domestic demand, and the site’s position over public water supply source protection zones. Policy SS03 asks only that the campus “minimises water and energy consumption”, in accordance with the plan’s water efficiency policy, DMP03 [1, p.79]. It contains no requirement on water supply, and its infrastructure requirements do not mention water [1, p.80].

4.5 The Council’s own Detailed Water Cycle Study does not assess the campus. Our October representation, paragraph 6.11, said that no detailed study followed the March 2024 scoping report. That was wrong, and I correct it here: the Council’s evidence base includes a Detailed Water Cycle Study, prepared by AECOM and dated June 2026 [17]. The study states: “E&SW does not supply mains water to developments that use open loop water cooling systems, such as certain types of data centres. In addition, it is not possible to guarantee supply to any development that does not adopt the most stringent water efficiency standards” [17, printed p.25]. It records that the company may introduce agreements for non-domestic supply “with a particular focus on data centres”, likely to require “closed-loop or near-zero-water cooling systems” [17, printed p.36]. The text of the study does not name the Arena Essex site, Lakeside or Policy SS03 anywhere. The plan’s water evidence therefore sets out the conditions on which a data centre might be supplied, but does not test them for the one data centre the plan allocates.

4.6 The Environment Agency says the deliverability of water supply must be secured in the plan. On Policy SS03, its Regulation 19 response says the policy’s water requirements are “a good basis, but the strategic deliverability point should be secured through the local plan rather than left solely to later connection enquiries” [18, p.18]. It has not been secured: the only enquiry made was for a demand the company would not supply, and none has been made for the design now proposed (paragraphs 4.1 to 4.3).

Fails: justified; effective.

5. Grid connection

5.1 The applicant says it has pursued a connection at Barking. Its Site Assessment states that “budget and formal connection application processes were progressed to test whether the necessary capacity could in fact be secured for development at the required scale. The planning application now proceeds on the basis that the point of connection will be Barking Grid Supply Point (GSP)” [19, para 4.6]. Its Planning Supporting Statement says the campus “avoids drawing power from the local distribution network” [20, para 10.2]. The campus’s annual electricity use at full capacity is 2,747,136 megawatt hours [21, Table 5.18, p.21], an average demand of about 314 megawatts (2,747,136 / 8,760 hours).

5.2 The national system operator holds no such application. “Where a project is connecting directly to the transmission system, NESO manages the connection” [7, p.2]. NESO states that it does “not hold a transmission connected demand application, offer, or agreement for a data centre where the connection site is recorded as Barking Grid Supply Point (GSP)”, and that “Total contracted transmission connected demand at Barking GSP is therefore 0” [7, p.2]. It holds no information on available demand capacity at Barking GSP and no assessment of constraints there [7, p.3].

5.3 The evidence does not show where or when the campus can connect. A Grid Supply Point is where the transmission network supplies the local distribution network. If the applications the applicant describes were made to the distribution network operator, the campus would draw on the network the applicant says it avoids (paragraph 5.1). If they were made under another connection site name, neither the plan’s evidence nor the application says so. If no transmission application has been made, there is none to assess. On any of these readings, no document before the examination shows where or when this campus can connect.

5.4 NESO holds no record of advice to the Council on the plan. “After searching our records and consulting the relevant teams, we confirm that we hold no recorded information within the scope of question 4” [7, p.3]. Question 4 asked for any response or advice to Thurrock Council on its Local Plan, Policy SS03 or data centre demand in Thurrock between 1 January 2024 and 1 October 2026. This adds to the October representation, paragraph 6.8, which records that no document in the evidence base mentions Barking Grid Supply Point or assesses a transmission connection for SS03.

5.5 Grid capacity is already delaying a data centre elsewhere in Essex. Press reports of October 2026 about a different site state that Microsoft ended its agreement as anchor tenant of a data centre planned by Nscale at Loughton, Essex, reported as 50 megawatts, after UK Power Networks said it could not supply enough power there “until the early to mid-2030s” [22], and that a UK Power Networks spokesperson said data centres “are awaiting works on the national transmission network which we do not own” [23]. These are reported statements about another site and are relied on as context only. Policy SS03 requires a campus “which has secure grid access” [1, p.79]. Nothing before the examination shows that this campus has it.

Fails: effective; consistent with national policy [24, paras 27(a), 87(a)].

6. National policy since the October representation

6.1 The draft National Policy Statement for Data Centres. The Department for Business, Innovation, Science and Trade published a draft National Policy Statement (NPS) for consultation in October 2026 [8]. It governs data centres directed into the regime for nationally significant infrastructure projects. For applications under the Town and Country Planning Act 1990 it states that it “may be a material consideration” [8, para 11, p.11]. It is a draft, and is relied on only for what it shows about the Government’s approach.

6.2 It does not apply its presumption of consent in the Green Belt. Among the exceptions to its presumption of consent is “When the data centre is located in the Green Belt” [8, para 84, p.30], and “The presumption of consent set out in section four of this NPS does not apply to development in the Green Belt” [8, para 349, p.76]. The SS03 site is in the Green Belt (October representation, Appendix A, A2). In plain terms, the Government’s proposed presumption in favour of data centres stops at the Green Belt. A data centre proposed there gets no presumption in its favour from the draft NPS. For a plan that alters the Green Belt boundary, as the HRA says this one does for SS03 (paragraph 3.3), the test in the December 2024 NPPF is that boundaries “should only be altered where exceptional circumstances are fully evidenced and justified” [24, para 145]. The plan’s case for exceptional circumstances rests on “the scale of housing and employment growth required” [1, para 4.2.6, p.34]. Policy SS03 provides no housing, and the plan itself describes the data centre as “additional growth beyond the EDNA forecasts” [1, para 4.2.4, p.34], that is, beyond the need identified by the Council’s own employment study, the Economic Development Needs Assessment. Exceptional circumstances for this use have not been evidenced (October representation, paragraphs 5.10 to 5.15).

6.3 It expects evidence from network bodies and water companies. In considering any data centre, the decision maker is to take into account “The necessary resource requirements of a proposed development, including energy requirements from grid connections or alternative sources, and water requirements”, “Any areas where capacity from the grid or environmental resources is already constrained”, and “Evidence … from electricity network bodies and water companies on infrastructure capacity, constraints and competing demands” [8, para 107, pp.35 to 36]. It states that “Grid connection delays and capacity constraints are a key challenge for new data centre developments, particularly in certain regions” [8, para 184, p.48], and that applicants “should disclose their anticipated water usage (estimated annual water use and peak day use) and efficiency and explain how this has influenced both their choice of location and cooling technology”, consulting the water companies [8, para 419, p.87]. Sections 4 and 5 show that the evidence the draft NPS expects is either absent or against the allocation.

6.4 SS03 would carry very limited weight in the decision it exists to support. The plan is examined against the December 2024 NPPF under the transitional arrangements [25, para 9.1; 9, Annex A para 8]. The planning application for the campus is decided under the August 2026 NPPF [9, Annex A para 1]. That Framework states: “Development plan policies (or parts of those policies) which are materially inconsistent with national decision-making policies in this Framework should be given very limited weight. The only exception to this is where they have been examined and adopted or made against this Framework” [9, Annex A para 2].

6.5 SS03 accepts the loss of the Local Wildlife Site and relies on “ecological mitigation required to off-set any loss of the existing on-site Local Wildlife Site” [1, p.78]. The August 2026 NPPF’s decision-making policies state: “If significant harm to biodiversity resulting from a development cannot be avoided (through locating on an alternative site with less harmful impacts), adequately mitigated or, as a last resort, compensated for, then the development should be refused” [9, policy N2(2), printed p.89]. They support development affecting a site identified as a local wildlife site in the development plan only where there would not be a significant adverse effect on its integrity, or the benefits “clearly outweigh the likely impact” on its features [9, policy N6(1)(c), printed p.92]. To the extent that SS03 accepts the loss of the Local Wildlife Site without first requiring that harm to be avoided, it is materially inconsistent with those policies. It would then carry very limited weight in the decision on the campus, because it will not have been examined against them. An allocation that cannot carry weight in the determination of the development it allocates is not effective.

6.6 Natural England says avoidance is required at this site, and the plan never tested whether the harm could be avoided. Its Regulation 19 response records that the site “has been confirmed through recent survey as a site containing Thames Terrace Grassland (TTG)” and is a Local Wildlife Site, and that “Appropriate avoidance, mitigation and compensation will be required to address significant wildlife impacts in this location” [14, p.14]. In the same response Natural England records that Thames Terrace Grassland sites “have recently been added to the Priority Habitats Inventory” [14, p.14]. It also advises that the policy “should preferably refer to the need to secure bespoke off-site compensation for Thames Terrace Grassland” [14, p.14]. The order matters. Avoidance of ecosystem damage must be considered first. The duty is on the Council and the developer to avoid the harm before turning to mitigation. Compensation is the last resort, not a substitute for the first step. The August 2026 NPPF sets the same order (paragraph 6.5). For an allocation, avoiding harm means testing whether the use could go on a site with less harmful impacts. That test was never carried out: the plan’s Integrated Impact Assessment did not compare locations for a data centre, and no other location was compared for this use (October representation, paragraphs 4.6 to 4.7 and 5.10 to 5.15). Policy SS03 skips the first step and starts from loss.

Fails: effective; consistent with national policy.

7. Further modifications sought

7.1 The main modification remains deletion of Policy SS03 and of the allocation, with the consequential modifications in the October representation, paragraphs 3.1 and 3.2.

7.2 If the policy is not deleted, the following are needed in addition to those in the October representation, paragraph 3.3:

g) before submission of the plan, correct the HRA’s screening and assessment of SS03, and assess the campus’s own pathways to the Thames Estuary and Marshes SPA and Ramsar site, including emissions from standby generation, against the wastewater measures of the undertaker that serves the borough; and

h) before submission of the plan, obtain and publish written confirmation from Essex & Suffolk Water that it can supply the campus as now designed, stating the volume, and from the electricity network operator or operators of the point, route, capacity and date of connection; record both in the Infrastructure Delivery Plan; and require in Policy SS03 that the cooling method and the maximum mains water demand are those confirmed.

7.3 Without that evidence, the allocation cannot be shown to be deliverable, and deletion is the only modification that makes the plan sound. There is time to act before submission: the Minister’s direction of 23 October 2026 moved the submission deadline for plans in the legacy system whose final Regulation 19 consultation ends by 31 December 2026 to 31 March 2027 [26].

8. Participation in the hearings

8.1 I ask to take part, on behalf of Protect Langdon, in the hearing sessions on Policy SS03 and on the Habitats Regulations Assessment (October representation, section 9). I consider it necessary for the reasons below.

8.2 My work identified the omission this consultation was extended for. I told Natural England in writing on 7 and 15 September 2026 that the HRA did not assess Policy SS18, and my representation of 14 October showed the Council the same (paragraph 2.2). Six days later the Council replaced the HRA and extended the consultation. The replacement still contains every SS03 error set out in the October representation (paragraph 3.2). The Inspector will need to test that against the Council’s account, and I have compared the two versions of the HRA word by word.

8.3 The Council says there are no further issues; the evidence shows otherwise. The Council was reported on 21 October 2026 as having reviewed its remaining consultation documents and found “no further issues” [5]. It had then held the October representation, which sets out the SS03 errors in the HRA, for more than a week, and those errors remain (paragraph 3.4). This document adds three more matters. The Council’s Detailed Water Cycle Study does not assess the one data centre the plan allocates (paragraph 4.5). No water supply is confirmed for any design (paragraphs 4.1 to 4.4). The national system operator holds no application at the stated point of connection (paragraph 5.2). Where the Council and I disagree on matters of this kind, written statements alone will not resolve them.

8.4 The grounds are technical and need to be explained and tested. They concern the ecology of a Local Wildlife Site and its Thames Terrace Grassland, the pathways from the campus to the Thames Estuary and Marshes SPA and Ramsar site, a water demand that the only enquiry made put at about 10.2 million litres a day, and an average electricity demand of about 314 megawatts. I am an ecologist. The Inspector, the Council and the applicant’s consultants should be able to question the analysis directly, and I should be able to answer them.

8.5 The evidence includes replies that only my information requests produced. The responses from Essex & Suffolk Water and the National Energy System Operator [6; 7] are not in the Council’s evidence base. I can explain what each shows and how it bears on the policy. The Inspector will also need to hear from Essex & Suffolk Water and the electricity network operators, whose confirmation the allocation lacks (paragraph 7.2).

8.6 Residents were not told what had changed. Residents who asked the Council in writing what the replacement HRA had changed were not told [11, section 7.2]. Taking part in the hearings allows that, and the case as a whole, to be put to the Inspector in person.

Documents relied on

Each entry gives the document, where it was published and the pages relied on. The two information responses are enclosed.

[1] Thurrock Local Plan 2024 to 2044, Regulation 19 Publication Version, August 2026

Thurrock Council. Relied on: pp.77 to 80; p.77; p.79; p.80; p.78; para 4.2.6, p.34; para 4.2.4, p.34. Source: link

[2] Thurrock Borough Local Plan Habitats Regulations Assessment, Draft Local Plan, Final report, July 2026 (replacement published 20 October 2026)

LUC for Thurrock Council. Relied on: pp.124, 125, 221; p.2; p.221; para 7.4, p.131; para 7.9, p.133; p.125; p.124; p.209; pp.285 to 286. Source: link

[3] Representation on Policy SS03, Former Arena Essex site and fishing lake, Lakeside, 12 October 2026

Dr Jackie Lighten on behalf of Protect Langdon. Submitted to Thurrock Council by email and on the consultation portal. Our Arena Essex page has the summary and the filed PDF.

[4] Representation on Policy SS18, New settlement north of the A13 (Lower Langdon and Corringham Park Farm), 14 October 2026

Dr Jackie Lighten on behalf of Protect Langdon. Submitted to Thurrock Council by email and on the consultation portal; published in full online. Read it on this website

[5] Thurrock’s Local Plan consultation extended until 10 November, 21 October 2026

Your Thurrock. Source: link

[6] Response to request EIR23263, 27 October 2026 (enclosed)

Northumbrian Water Limited, trading as Essex & Suffolk Water, under the Environmental Information Regulations 2004. Relied on: pp.2 to 3; p.3. Enclosed with the filed copy; not published on this website.

[7] Response to request FOI/26/246, 28 October 2026 (enclosed)

National Energy System Operator, under the Environmental Information Regulations 2004. Relied on: pp.2 to 3; p.2; p.3. Enclosed with the filed copy; not published on this website.

[8] Initial Proposal for a National Policy Statement for Data Centres, October 2026 (consultation draft)

Department for Business, Innovation, Science and Trade. Relied on: paras 84, 107, 349; para 11, p.11; para 84, p.30; para 349, p.76; para 107, pp.35 to 36; para 184, p.48; para 419, p.87. Source: link

[9] National Planning Policy Framework, August 2026

Ministry of Housing, Communities and Local Government. Relied on: Annex A para 2; Annex A para 8; Annex A para 1; policy N2(2), printed p.89; policy N6(1)(c), printed p.92. Source: link

[10] Local Plan Regulation 19 consultation, web page, checked 9 November 2026

Thurrock Council. Source: link

[11] Supplementary representation on Policy SS18, dated 10 November 2026 and filed on 9 November 2026, with Annex A (replies to information requests)

Dr Jackie Lighten on behalf of Protect Langdon. Relied on: section 7.1; Annex A, item A9; section 7.3; section 7.2. Read it on this website

[12] Thurrock Borough Local Plan Habitats Regulations Assessment, Draft Local Plan, Final report, July 2026 (as published in August 2026, since replaced)

LUC for Thurrock Council. Relied on: p.2. Source: link

[13] Thurrock Infrastructure Delivery Plan, July 2026

Thurrock Council. Relied on: p.61. Source: link

[14] Regulation 19 response to the Thurrock Local Plan, ref 557779, 14 October 2026

Natural England. Held by the Council. Relied on: p.5; p.14.

[15] Consultation response on application 25/00573/OUT, 13 August 2026

Essex & Suffolk Water. Thurrock Council planning register. Source: link

[16] Applicant note, 13 November 2025, application 25/00573/OUT

Thurrock Council planning register. Relied on: p.1. Source: link

[17] Thurrock Detailed Water Cycle Study, June 2026

AECOM for Thurrock Council. Relied on: printed p.25; printed p.36. Source: link

[18] Regulation 19 response to the Thurrock Local Plan, ref AE/2026/131362/CS-01/SB1, 13 October 2026

Environment Agency. Held by the Council. Relied on: p.18.

[19] Site Assessment, July 2026, application 25/00573/OUT

Thurrock Council planning register. Relied on: para 4.6. Source: link

[20] Planning Supporting Statement, April 2025, application 25/00573/OUT

Thurrock Council planning register. Relied on: para 10.2. Source: link

[21] Environmental Statement, Chapter 5, Climate Change and Greenhouse Gases, application 25/00573/OUT

Thurrock Council planning register. Relied on: Table 5.18, p.21. Source: link

[22] Report on Microsoft’s withdrawal from the Nscale data centre at Loughton, 18 October 2026

Gwyn Topham, The Guardian, as syndicated on AOL. Source: link

[23] Report on Microsoft’s withdrawal from the Nscale data centre at Loughton, 19 October 2026

The Register. Source: link

[24] National Planning Policy Framework, December 2024

Ministry of Housing, Communities and Local Government. Relied on: paras 27(a), 87(a); para 145. Source: link

[25] Cabinet report, Thurrock Local Plan 2024 to 2044, Regulation 19 Version

Thurrock Council. Relied on: para 9.1. Source: link

[26] Letter to council leaders on legacy system local plans, 23 October 2026

Rt Hon Matthew Pennycook MP, Housing Minister. Published on gov.uk. Source: link